3/2
Fished wire to and installed box for fam room light fixture, wired dual switch box in hall. Installed outlets in fam room. Ran wire to computer outlets, nearly completed fam room circuit. Pulled wire (14/3) for lights in downstairs utility. Installed 4 gang outlets for computer.
3/3
Moved fam room light to new circuit. Moved tv outlets to new circuit. Readied FR circuit and small br circuit for electrician to connect. Spent time on 3 way two light circuit w/ no success. Will ask Mike Briggs tomorrow.
3/4
Briggs electric replaced fuse box w/ 200 amp main breaker and both interior subpanels with one main subpanel in the basement. All 3 circuits we had done worked on 1st try. The boys light didn't get hooked back up. Ran cable to outlet and to the light fixture and used the breaker fo rthe bathroom outlet to power light temporarily. Getting better at fishing wire and figuring out circuits. WE HAVE NEW SERVICE PANELS!!!
3/5
Removed several old cables from ceiling. Installed 2nd light in utility 3-way light system. Melanie planted cherry tree in 5 gallon bucket and put 24 5 gallon buckets of sand on th egarden spots.
3/6
Mike briggs dropped off 3 lenghts of PVC pipe for our line to the garage. He also gave us some cable for our ranges and for the cable to the garage subpanel. (there is no power in the garage yet). Melanie got another 14 buckets of sand for the garden.
3/8
Spoke in church.
3/9
Helped replace main water line at mom's Pocatello rental. I dug under a 6 foot sidewalk and into the meter pipe. Got connected and 1/3 buried.
3/10
Tried to run wire to switch in downstairs bathroom. Ran into blocked joice space.
3/11
Drew wiring diagram for garage. Looked for a piaon on Craigslist.
3/12
Bought shovels and rake. Dug trench for conduit to garage. Tested one light. Dug 1/2 way under sidewalk. Pin nailer arrived today. Bought Melanie a big pitunia hanging basket. Broadheads offered us their piano.
3/13
Mom and Dad finished digging tunnel while I was at work. Dad and I ran the conduit and put the cable in as we glued the parts together. Wired the garage subpanel.
3/14
Widened opening for conduit w/ leatherman file while Melanie filled in the trench for the garage electrical. Wired main breaker--50 amp. will probably need to replace w/ thicker wire to go to 100 amp. Installed an dwired 2 flourescent lights and switch--We now have light in the garage!!
Ran new source wire to boy's bathroom. Wored boy's bath light and fan. Installed new plug in boy's wal. Fixed neighbor's bread box. Got called as primary teacher today.